W18_SSG_Resource Leveling


PROBLEM DEFINITION

Having developed the cost baseline profile based on Week 16 CPM schedule, I find that resource allocation is not preferable where the resource is so demanding in the beginning and the end of the course. I prefer the time allocation is more “flat” on weekly basis.

Continue reading

1 Comment

Filed under Sutoyo S, Week 18

W18_APE_Berth Occupancy Rate Exercise Using Crystal Ball Software


  1. Problem Definition

BOR or Berth Occupancy Rate is one of key element to be used for any port investment assessment. Using BOR information, the Designer then able for designing the wharf size required for vessels berthing. Indeed, the composition of each port BOR depend on logistic planning for cargo and for our port the most important cargo will be sulphur pallets deliver in containers. For W18 blog i will exercise sulphur BOR using crystal ball software.

Continue reading